A priority rule-based heuristic for resource investment project scheduling problem with discounted cash flows and tardiness penalties (Q1036260)
From MaRDI portal
| This is the item page for this Wikibase entity, intended for internal use and editing purposes. Please use this page instead for the normal view: A priority rule-based heuristic for resource investment project scheduling problem with discounted cash flows and tardiness penalties |
scientific article; zbMATH DE number 5632433
| Language | Label | Description | Also known as |
|---|---|---|---|
| English | A priority rule-based heuristic for resource investment project scheduling problem with discounted cash flows and tardiness penalties |
scientific article; zbMATH DE number 5632433 |
Statements
A priority rule-based heuristic for resource investment project scheduling problem with discounted cash flows and tardiness penalties (English)
0 references
13 November 2009
0 references
Summary: The resource investment problem with discounted cash flows (RIPDCFs) is a class of project scheduling problems. In RIPDCF, the availability levels of the resources are considered decision variables, and the goal is to find a schedule such that the net present value of the project cash flows optimizes. In this paper, we consider a new RIPDCF in which tardiness of project is permitted with defined penalty. We mathematically formulated the problem and developed a heuristic method to solve it. The results of the performance analysis of the proposed method show an effective solution approach to the problem.
0 references
availability levels
0 references
tardiness
0 references
0 references
0 references
0 references
0 references
0 references
0 references
0 references
0 references