Computing latest starting times of activities in interval-valued networks with minimal time lags
From MaRDI portal
Publication:1044116
DOI10.1016/j.ejor.2009.01.051zbMath1177.90191OpenAlexW2003101234MaRDI QIDQ1044116
Siamak Haji Yakhchali, Seyed Hassan Ghodsipour
Publication date: 10 December 2009
Published in: European Journal of Operational Research (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1016/j.ejor.2009.01.051
Deterministic scheduling theory in operations research (90B35) Fuzzy and other nonstochastic uncertainty mathematical programming (90C70)
Related Items (8)
Fuzzy finish time modeling for project scheduling ⋮ Evaluation of the quantiles and superquantiles of the makespan in interval valued activity networks ⋮ Theory and application of reciprocal transformation of “path problem” and “time float problem” ⋮ Multiple criteria group decision-making with generalized interval-valued fuzzy numbers based on signed distances and incomplete weights ⋮ A path enumeration approach for the analysis of critical activities in fuzzy networks ⋮ On the latest starting times and criticality of activities in a network with imprecise durations ⋮ A node-weighted rooted tree (NWRT) method to find project characteristics and critical path in a triangular fuzzy project network ⋮ Simplifying activity networks under generalized precedence relations to extended CPM networks
Cites Work
- Unnamed Item
- Unnamed Item
- Unnamed Item
- Unnamed Item
- Erratum to ``On computing the latest starting times and floats of activities in a network with imprecise durations [Fuzzy sets and systems 150 (2005) 53-76]
- Applying fuzzy method for measuring criticality in project network
- A simple approach to fuzzy critical path analysis in project networks
- Project network analysis with fuzzy activity times
- Fuzzy sets and systems. Theory and applications
- The use of fuzzy variables in PERT
- Fuzzy sets as a basis for a theory of possibility
- Using fuzzy set theory in a scheduling problem: A case study
- Project scheduling. A research handbook.
- On computing the latest starting times and floats of activities in a network with imprecise durations
- Project scheduling under uncertainty: survey and research potentials
- Stochastic and fuzzy PERT
- Fuzzy scheduling: Modelling flexible constraints vs. coping with incomplete knowledge
- On latest starting times and floats in activity networks with ill-known durations
- On the hardness of evaluating criticality of activities in a planar network with duration intervals
- Application of fuzzy distributions on project management
- Analysis of critical paths in a project network with fuzzy activity times
- Fuzzy-Network Planning - FNET
- Critical-Path Planning and Scheduling: Mathematical Basis
- Interval Analysis in Scheduling
- Bounding the Project Completion Time Distribution in PERT Networks
- Operations on fuzzy numbers
- Application of a Technique for Research and Development Program Evaluation
- Criticality analysis in activity-on-node networks with minimal time lags
- Critical path analysis in the network with fuzzy activity times
- The computational complexity of the criticality problems in a network with interval activity times
This page was built for publication: Computing latest starting times of activities in interval-valued networks with minimal time lags