Heuristics for permutation flow shop scheduling with batch setup times
From MaRDI portal
Publication:1814870
DOI10.1007/BF01539731zbMath0858.90079OpenAlexW2083984163WikidataQ57633992 ScholiaQ57633992MaRDI QIDQ1814870
Frank Werner, Thomas Tautenhahn, Yuri N. Sotskov
Publication date: 31 October 1996
Published in: OR Spektrum (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1007/bf01539731
heuristicsbeam searchmakespangroup technologysum of completion timespermutation flow shop schedulingbatch setup timesmanufactoring cells
Related Items
A comprehensive review of flowshop group scheduling literature, A branch \(\&\) bound method for the general-shop problem with sequence dependent setup-times, Scheduling with batching: A review, Local search heuristics for two-stage flow shop problems with secondary criterion, Flowshop-scheduling problems with makespan criterion: a review, A comparison of heuristic algorithms for flow shop scheduling problems with setup times and limited batch size
Cites Work
- On the heuristic solution of the permutation flow shop problem by path algorithms
- Some efficient heuristic methods for the flow shop sequencing problem
- Minimizing the sum of the job completion times in the two-machine flow shop by Lagrangian relaxation
- Batching in single operation manufacturing systems
- Single facility scheduling with multiple job classes
- One-pass batching algorithms for the one-machine problem
- A new heuristic method for the flow shop sequencing problem
- Constructive heuristic algorithms for the open shop problem
- The complexity of one-machine batching problems
- Simulated annealing procedures for forming machine cells in group technology
- Two-machine shop scheduling problems with batch processing
- Insertion techniques for the heuristic solution of the job shop problem
- Decomposition approaches in permutation scheduling problems with application to the M-machine flow shop scheduling problems
- A new heuristic for the n-job, M-machine flow-shop problem
- Benchmarks for basic scheduling problems
- Optimal two- and three-stage production schedules with setup times included
- Batching to Minimize Flow Times on One Machine
- The Single Machine Early/Tardy Problem
- The Lessons of Flowshop Scheduling Research
- Tabu Search—Part I
- Integrating Scheduling with Batching and Lot-Sizing: A Review of Algorithms and Complexity
- Tabu Search—Part II
- Procedures for Estimating Optimal Solution Values for Large Combinatorial Problems
- The Complexity of Flowshop and Jobshop Scheduling
- Improving the Efficiency of Tabu Search for Machine Sequencing Problems
- A Heuristic Algorithm for the n Job, m Machine Sequencing Problem
- Unnamed Item
- Unnamed Item
- Unnamed Item
- Unnamed Item