A robust time-cost-quality-energy-environment trade-off with resource-constrained in project management: a case study for a bridge construction project
DOI10.3934/jimo.2020158zbMath1499.90081OpenAlexW3095732480MaRDI QIDQ2076443
Amir Hossein Khameneh, Reza Lotfi, Erfan Babaee Tirkolaee, Zahra Yadegari, Gerhard-Wilhelm Weber, Seyed Hossein Hosseini
Publication date: 16 February 2022
Published in: Journal of Industrial and Management Optimization (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.3934/jimo.2020158
multi-objective optimizationrobust optimizationaugmented \(\varepsilon\)-constraint methodtime-cost-quality-energy-environment trade-off
Multi-objective and goal programming (90C29) Management decision making, including multiple objectives (90B50) Deterministic scheduling theory in operations research (90B35) Robustness in mathematical programming (90C17)
Related Items (16)
Cites Work
- Unnamed Item
- A robust optimization approach to closed-loop supply chain network design under uncertainty
- RCMARS: robustification of CMARS with different scenarios under polyhedral uncertainty set
- The discrete time/cost trade-off problem: Extensions and heuristic procedures
- Effective implementation of the \(\varepsilon \)-constraint method in multi-objective mathematical programming problems
- Project management with time, cost, and quality considerations
- Robust solutions of linear programming problems contaminated with uncertain data
- A heuristic procedure to solve the project staffing problem with discrete time/resource trade-offs and personnel scheduling constraints
- Multi-objective multi-mode resource constrained project scheduling problem using Pareto-based algorithms
- Interdependent demand in the two-period newsvendor problem
- A solution procedure for the discrete time, cost and quality tradeoff problem using electromagnetic scatter search
- A genetic algorithm approach for the time-cost trade-off in PERT networks
- New computational results on the discrete time/cost trade-off problem in project networks
- The stochastic time–cost tradeoff problem: A robust optimization approach
- A Horizon-Varying, Zero-One Approach to Project Scheduling
- A Simple CPM Time-Cost Tradeoff Algorithm
- Technical Note—Convex Programming with Set-Inclusive Constraints and Applications to Inexact Linear Programming
- Integrated time–cost tradeoff and resources leveling problems with allowed activity splitting
This page was built for publication: A robust time-cost-quality-energy-environment trade-off with resource-constrained in project management: a case study for a bridge construction project