A branch-and-bound algorithm for the single machine sequence-dependent group scheduling problem with earliness and tardiness penalties
DOI10.1016/j.apm.2015.01.069zbMath1443.90041OpenAlexW2074384335MaRDI QIDQ2285347
Nasser Salmasi, Taha Keshavarz, Savelsbergh, Martin W. P.
Publication date: 8 January 2020
Published in: Applied Mathematical Modelling (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1016/j.apm.2015.01.069
branch-and-bound algorithmLagrangian relaxationgroup schedulingtime-indexed formulationsequence-dependent setup timeminimization of earliness and tardiness
Polyhedral combinatorics, branch-and-bound, branch-and-cut (90C57) Deterministic scheduling theory in operations research (90B35) Mathematical modeling or simulation for problems pertaining to operations research and mathematical programming (90-10)
Related Items (9)
Uses Software
Cites Work
- An exact algorithm for the single-machine total weighted tardiness problem with sequence-dependent setup times
- Single-machine group scheduling with general deterioration and learning effects
- Exact algorithm over an arc-time-indexed formulation for parallel machine scheduling problems
- A faster branch-and-bound algorithm for the earliness-tardiness scheduling problem
- A hybrid genetic algorithm with dominance properties for single machine scheduling with dependent penalties
- Formulating the single machine sequencing problem with release dates as a mixed integer program
- Single machine scheduling with batch set-up times to minimize maximum lateness
- Earliness-tardiness scheduling with setup considerations
- Single machine scheduling with symmetric earliness and tardiness penalties
- Batch scheduling to minimize total completion time
- Scheduling with batching: A review
- An exact algorithm for single-machine scheduling without machine idle time
- Branch and bound algorithms for single machine scheduling with batching to minimize the number of late jobs
- Lower bounds for the earliness-tardiness scheduling problem on parallel machines with distinct due dates
- Near-Optimal Solutions of Large-Scale Single-Machine Scheduling Problems
- Time-Indexed Formulations and the Total Weighted Tardiness Problem
- New Exact Algorithms for One-Machine Earliness-Tardiness Scheduling
- An Exact Algorithm for the Single-Machine Earliness–Tardiness Scheduling Problem
- The Lagrangian Relaxation Method for Solving Integer Programming Problems
- On the Complexity of Scheduling with Batch Setup Times
- A Branch-and-Bound Algorithm for Single-Machine Earliness–Tardiness Scheduling with Idle Time
- Time-Indexed Formulations for Machine Scheduling Problems: Column Generation
- Optimal timing schedules in earliness-tardiness single machine sequencing
- Scheduling
This page was built for publication: A branch-and-bound algorithm for the single machine sequence-dependent group scheduling problem with earliness and tardiness penalties