A scatter search heuristic for maximising the net present value of a resource-constrained project with fixed activity cash flows
From MaRDI portal
Publication:3163363
DOI10.1080/00207540802010781zbMath1197.90235OpenAlexW2047086382MaRDI QIDQ3163363
Publication date: 25 October 2010
Published in: International Journal of Production Research (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1080/00207540802010781
Deterministic scheduling theory in operations research (90B35) Approximation methods and heuristics in mathematical programming (90C59)
Related Items (9)
Temporal linear relaxation in IBM ILOG CP optimizer ⋮ Optimization Strategies for Resource-Constrained Project Scheduling Problems in Underground Mining ⋮ Models and solution procedures for the resource-constrained project scheduling problem with general temporal constraints and calendars ⋮ Going to the core of hard resource-constrained project scheduling instances ⋮ An analysis of network and resource indicators for resource-constrained project scheduling problem instances ⋮ New resource-constrained project scheduling instances for testing (meta-)heuristic scheduling algorithms ⋮ An updated survey of variants and extensions of the resource-constrained project scheduling problem ⋮ Capital- and resource-constrained project scheduling with net present value optimization ⋮ Generic negotiation mechanisms with side payments -- design, analysis and application for decentralized resource-constrained multi-project scheduling problems
Uses Software
Cites Work
- Unnamed Item
- Experimental investigation of heuristics for resource-constrained project scheduling: an update
- Scheduling subject to resource constraints: Classification and complexity
- An iterative scheduling technique for resource-constrained project scheduling
- An optimal procedure for the resource-constrained project scheduling problem with discounted cash flows and generalized precedence relations
- A steepest ascent approach to maximizing the net present value of projects
- Resource-constrained project scheduling: A critical activity reordering heuristic
- Resource-constrained project scheduling: A survey of recent developments.
- Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem
- Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models
- Resource-constrained project scheduling: Notation, classification, models, and methods
- An electromagnetism-like mechanism for global optimization
- Rangen: A random network generator for activity-on-the-node networks
- Principles of scatter search
- A hybrid scatter search/electromagnetism meta-heuristic for project scheduling
- On Maximizing the Net Present Value of a Project Under Renewable Resource Constraints
- A Decomposition-Based Genetic Algorithm for the Resource-Constrained Project-Scheduling Problem
- A Branch-and-Bound Procedure for the Multiple Resource-Constrained Project Scheduling Problem
- Project scheduling: The effects of problem structure on heuristic performance
- A bidirectional heuristic for maximizing the net present value of large-scale projects subject to limited resources
- An Experimental Investigation and Comparative Evaluation of Production Line Balancing Techniques
- The payment scheduling problem
This page was built for publication: A scatter search heuristic for maximising the net present value of a resource-constrained project with fixed activity cash flows