An efficient metaheuristic for integrated scheduling and staffing IT projects based on a generalized minimum cost flow network
DOI10.1002/nav.21476zbMath1248.90056OpenAlexW2150875910MaRDI QIDQ3166685
Christian Heimerl, Rainer Kolisch
Publication date: 15 October 2012
Published in: Naval Research Logistics (NRL) (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1002/nav.21476
project schedulingtabu searchgenetic algorithmmetaheuristicresource assignmentgeneralized minimum cost flowproject staffingmultiskilled resources
Deterministic scheduling theory in operations research (90B35) Approximation methods and heuristics in mathematical programming (90C59) Theory of organizations, manpower planning in operations research (90B70)
Related Items (11)
Cites Work
- Unnamed Item
- Unnamed Item
- Staff scheduling and rostering: a review of applications, methods and models.
- Resource levelling for projects with schedule-dependent time windows
- Staff scheduling at the United States postal Service
- Scheduling and staffing multiple projects with a multi-skilled workforce
- A Branch-and-Cut Procedure for the Multimode Resource-Constrained Project-Scheduling Problem
- Work assignment to and qualification of multi-skilled human resources under knowledge depreciation and company skill level targets
- Decision-making support system for human resource allocation in product development projects
- Handbook of metaheuristics
This page was built for publication: An efficient metaheuristic for integrated scheduling and staffing IT projects based on a generalized minimum cost flow network