Minimizing the total weighted completion time in a two-machine proportionate flow shop with different machine speeds
From MaRDI portal
Publication:5478829
DOI10.1080/00207540500268780zbMath1095.90037OpenAlexW2049955857MaRDI QIDQ5478829
Suk-Hun Yoon, Sung-Jin Chung, Byung-Cheon Choi
Publication date: 13 July 2006
Full work available at URL: https://doi.org/10.1080/00207540500268780
NP-completeMachine speedProportionate flow shopWeighted shortest processing timeWorst-case performance ratio
Related Items (3)
A note: Maximizing the weighted number of just-in-time jobs on a proportionate flowshop ⋮ Flow shops with machine maintenance: ordered and proportionate cases ⋮ Two-machine flow-shop scheduling with equal processing time on the second machine for minimizing total weighted completion time
Cites Work
- Minimizing total weighted completion time in a proportionate flow shop
- Some results of the worst-case analysis for flow shop scheduling
- Generalized pairwise interchanges and machine scheduling
- Polynomial time approximation algorithms for machine scheduling: Ten open problems
- The three-machine proportionate flow shop problem with unequal machine speeds
- Minimizing Total Completion Time in a Two-Machine Flowshop: Analysis of Special Cases
- Generating Experimental Data for Computational Testing with Machine Scheduling Applications
- Focused Scheduling in Proportionate Flowshops
- Flowshop Sequencing Problem with Ordered Processing Time Matrices
- Flowshop sequencing problem with ordered processing time matrices: A general case
This page was built for publication: Minimizing the total weighted completion time in a two-machine proportionate flow shop with different machine speeds