Minimizing Resource Availability Costs in Time-Limited Project Networks
From MaRDI portal
Publication:5689376
DOI10.1287/mnsc.41.10.1590zbMath0861.90071OpenAlexW2066960045MaRDI QIDQ5689376
Publication date: 6 January 1997
Published in: Management Science (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1287/mnsc.41.10.1590
Related Items (37)
Mixed integer programming formulations for the biomass truck scheduling problem ⋮ A metaheuristic solution approach for the time-constrained project scheduling problem ⋮ An exact algorithm for an integrated project staffing problem with a homogeneous workforce ⋮ Time-constrained project scheduling ⋮ Multi-mode resource constrained multi-project scheduling and resource portfolio problem ⋮ Multi-mode resource availability cost problem with recruitment and release dates for resources ⋮ A genetic algorithm for resource investment problem with discounted cash flows ⋮ Evolutionary algorithms for multi-objective stochastic resource availability cost problem ⋮ A capacity-oriented hierarchical approach to single-item and small-batch production planning using project-scheduling methods ⋮ A genetic algorithm for resource investment project scheduling problem, tardiness permitted with penalty ⋮ Robust optimization models for project scheduling with resource availability cost ⋮ Solving project scheduling problem with the philosophy of fuzzy random programming ⋮ Robust decision trees for the multi-mode project scheduling problem with a resource investment objective and uncertain activity duration ⋮ Order-based neighborhoods for project scheduling with nonregular objective functions. ⋮ The multi-mode resource investment problem: a benchmark library and a computational study of lower and upper bounds ⋮ Multimode preemptive resource investment problem subject to due dates for activities: formulation and solution procedure ⋮ A cost optimization model for multiresource leveling problem without project duration constraint ⋮ SCHEDULING THE HARVESTING OPERATIONS OF A FOREST BLOCK: A CASE STUDY ⋮ The bilevel optimisation of a multi-agent project scheduling and staffing problem ⋮ An effective heuristic for project scheduling with resource availability cost ⋮ Mixed-integer linear programming and constraint programming formulations for solving resource availability cost problems ⋮ Solving the resource availability cost problem in project scheduling by path relinking and genetic algorithm ⋮ Fuzzy project scheduling problem and its hybrid intelligent algorithm ⋮ A hybrid framework for over-constrained generalized resource-constrained project scheduling problems ⋮ An exact algorithm for minimizing resource availability costs in project scheduling ⋮ An efficient genetic algorithm to maximize net present value of project payments under inflation and bonus-penalty policy in resource investment problem ⋮ Um algoritmo exato para o problema de programação de projetos com custo de disponibilidade de recursos e múltiplos modos ⋮ Resource-constrained project scheduling: Notation, classification, models, and methods ⋮ Resource levelling for projects with schedule-dependent time windows ⋮ A MULTI-OBJECTIVE RISK-BASED FRAMEWORK FOR MISSION CAPABILITY PLANNING ⋮ A parameter-tuned genetic algorithm for the resource investment problem with discounted cash flows and generalized precedence relations ⋮ A priority rule-based heuristic for resource investment project scheduling problem with discounted cash flows and tardiness penalties ⋮ Polyhedral Results and Branch-and-Cut for the Resource Loading Problem ⋮ Heuristics for multimode scheduling problems with dedicated resources ⋮ Scatter search for project scheduling with resource availability cost ⋮ Project scheduling problem with stochastic activity duration times ⋮ Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints
This page was built for publication: Minimizing Resource Availability Costs in Time-Limited Project Networks