A path enumeration approach for the analysis of critical activities in fuzzy networks
From MaRDI portal
Publication:713412
DOI10.1016/j.ins.2012.01.025zbMath1250.90040OpenAlexW2075204503MaRDI QIDQ713412
Publication date: 29 October 2012
Published in: Information Sciences (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1016/j.ins.2012.01.025
Related Items (1)
Uses Software
Cites Work
- Unnamed Item
- Unnamed Item
- Unnamed Item
- Erratum to ``On computing the latest starting times and floats of activities in a network with imprecise durations [Fuzzy sets and systems 150 (2005) 53-76]
- Applying fuzzy method for measuring criticality in project network
- Is there a need for fuzzy logic?
- On the latest starting times and criticality of activities in a network with imprecise durations
- Three-objective fuzzy chance-constrained programming model for multiproject and multi-item investment combination
- A simple approach to fuzzy critical path analysis in project networks
- Computing latest starting times of activities in interval-valued networks with minimal time lags
- The use of fuzzy variables in PERT
- Fuzzy sets as a basis for a theory of possibility
- Using fuzzy set theory in a scheduling problem: A case study
- PSPLIB -- a project scheduling problem library
- Project scheduling. A research handbook.
- On computing the latest starting times and floats of activities in a network with imprecise durations
- Project scheduling under uncertainty: survey and research potentials
- Stochastic and fuzzy PERT
- Fuzzy scheduling: Modelling flexible constraints vs. coping with incomplete knowledge
- On latest starting times and floats in activity networks with ill-known durations
- On the hardness of evaluating criticality of activities in a planar network with duration intervals
- Analysis of critical paths in a project network with fuzzy activity times
- Toward a generalized theory of uncertainty (GTU) -- an outline
- Fuzzy-Network Planning - FNET
- Complexity of the minimum-dummy-activities problem in a pert network
- Interval Analysis in Scheduling
- The Analysis of Activity Networks Under Generalized Precedence Relations (GPRs)
- Operations on fuzzy numbers
- Application of a Technique for Research and Development Program Evaluation
- Characterization and Generation of a General Class of Resource-Constrained Project Scheduling Problems
- Critical path analysis in the network with fuzzy activity times
- The computational complexity of the criticality problems in a network with interval activity times
This page was built for publication: A path enumeration approach for the analysis of critical activities in fuzzy networks