A (\(\frac {4}{3}\))-approximation algorithm for a special case of the two machine flow shop problem with several availability constraints
From MaRDI portal
Publication:732786
DOI10.1007/s11590-009-0137-6zbMath1176.90218OpenAlexW2058254191MaRDI QIDQ732786
Publication date: 15 October 2009
Published in: Optimization Letters (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1007/s11590-009-0137-6
Deterministic scheduling theory in operations research (90B35) Approximation methods and heuristics in mathematical programming (90C59)
Related Items (8)
Scheduling jobs with truncated exponential learning functions ⋮ Optimal due-date assignment problem with learning effect and resource-dependent processing times ⋮ The two-stage assembly flow shop scheduling with an availability constraint: worst case analysis ⋮ A PTAS for a particular case of the two-machine flow shop with limited machine availability ⋮ A polynomial-time approximation scheme for the two machine flow shop problem with several availability constraints ⋮ Single-machine scheduling with nonlinear deterioration ⋮ Minimizing makespan in a two-machine flow shop with effects of deterioration and learning ⋮ Approximation results for the two-machine job shop under limited machine availability
Cites Work
- Approximation results for flow shop scheduling problems with machine availability constraints
- Two-machine flowshop scheduling with availability constraints
- Minimizing the makespan in the two-machine flowshop scheduling problem with an availability constraint
- Non-preemptive two-machine open shop scheduling with non-availability constraints
- An improved heuristic for two-machine flowshop scheduling with an availability constraint
- Two-machine flowshop scheduling with consecutive availability constraints
- An improved approximation algorithm for two-machine flow shop scheduling with an availability constraint
- Optimal two- and three-stage production schedules with setup times included
- An FPTAS for scheduling a two-machine flowshop with one unavailability interval
- Two-machine flow shops with limited machine availability
This page was built for publication: A (\(\frac {4}{3}\))-approximation algorithm for a special case of the two machine flow shop problem with several availability constraints