A hybrid exact method for a scheduling problem with a continuous resource and energy constraints
From MaRDI portal
Publication:890001
DOI10.1007/s10601-015-9192-zzbMath1327.90073OpenAlexW2144013806MaRDI QIDQ890001
Pierre Lopez, Christian Artigues, Margaux Nattaf
Publication date: 9 November 2015
Published in: Constraints (Search for Journal in Brave)
Full work available at URL: https://doi.org/10.1007/s10601-015-9192-z
Mixed integer programming (90C11) Deterministic scheduling theory in operations research (90B35) Approximation methods and heuristics in mathematical programming (90C59)
Related Items (7)
Energetic reasoning and mixed-integer linear programming for scheduling with a continuous resource and linear efficiency functions ⋮ Scheduling under a non-reversible energy source: an application of piecewise linear bounding of non-linear demand/cost functions ⋮ Minimizing grid capacity in preemptive electric vehicle charging orchestration: complexity, exact and heuristic approaches ⋮ Allocation of limited resources under quadratic constraints ⋮ Cumulative scheduling with variable task profiles and concave piecewise linear processing rate functions ⋮ Polyhedral results and valid inequalities for the continuous energy-constrained scheduling problem ⋮ Scheduling aspects in keyword extraction problem
Cites Work
- Unnamed Item
- MIP models for resource-constrained project scheduling with flexible resource profiles
- Scheduling malleable tasks on parallel processors to minimize the makespan
- Project scheduling with finite or infinite number of activity processing modes -- a survey
- Event-based MILP models for resource-constrained project scheduling problems
- A priority-rule method for project scheduling with work-content constraints
- Constraint-based scheduling: Applying constraint programming to scheduling problems.
- Energetic reasoning for energy-constrained scheduling with a continuous resource
- A branch-and-cut algorithm for scheduling of projects with variable-intensity activities
- Algorithms for Reporting and Counting Geometric Intersections
- Une méthode arborescente pour résoudre les problèmes cumulatifs
This page was built for publication: A hybrid exact method for a scheduling problem with a continuous resource and energy constraints